Compton WWTP Flood Wall
Project Type: Water & Wastewater,
Owner: City of Branson
Location: Branson, MO
KCI Role: General Contractor
Value: $9,962.10
Delivery Method: Bid Build
Completion Date: October 2024
Designer: HDR Engineering
KCI was contracted to construct a flood wall around the City of Branson WWTP, consisting of 4K CY of embankment to level the site for a new 2155 LF structural sheet pile wall (112K SF), with pile supported CIP entrance and gate structures for influent and outflow piping to keep the plan operational in a flood condition. The project also required KCI overlaid the roadway/lot with asphalt and some replacement PCCP Pavement, with 144 LF of new RCP to handle storm flow Includes mechanical piping and tie-in modifications to new gate structures and electrical upgrades.