Lakeside 370 Levee Pump Stations
Despite almost 9 months of politically related delays prior to starting work, KCi began work in fall of 2005 on two new pump stations to accommodate the new 100-year levee being installed to facilitate new development. Construction of the two concrete pump stations was completed in the 12-month schedule, while dealing with a constantly flooding site directly underneath high-voltage power transmission lines. One station was built into the new 100-year levee built by others, and one station was cut into the 30-year Dardenne Creek farm levee.
“I would like to thank KCI Construction for the teamwork demonstrated in the construction of the Pump Stations.”
Mike Yerion, Project Manager – City of St. Peters
Size: 2 pump stations
Owner: City of St. Peters
KCI Role: General Contractor
Value: $5,400,000
Delivery Method: Bid Build
Completion: December 2006
Designer: Jacobs