Header image for this page is an image of: Dcim101mediadji 0045.jpg

Jefferson Barracks Bridge Rehabilitation

Project Type: Transportation,

Owner: MoDOT

KCI Role: General Contractor

Value: $49,997,800

Delivery Method: Bid Build

Completion Date: 2023

Designer: Wiss, Janney, Elstner Associates

MoDOT determined the Jefferson Barracks bridges along I-255 need to be rehabilitated to help ensure that the bridge remains serviceable and in good condition for the foreseeable future. KCI was contracted to complete the project which included the rehabilitation of the Jefferson Barracks bridges (46K SY) with Latex and Polyester Polymer overlays, rehabilitation of the Koch Road bridges (2855 SY) with Latex overlay, painting of tie arches, expansion joint replacement, deck repairs, and barrier replacements.