Header image for this page is an image of: Page Olive Connector 01 Copy 2

Page Olive Connector / Highway 141

Project Type: Design/Build,

Size: 2 Miles

Owner: St. Louis County

Location: St. Louis, MO

KCI Role: General Contractor

Value: $52,500,000

Delivery Method: Design Build

Completion Date: 2012

Designer: Jacobs

KCI submitted the highest scored technical proposal for this design-build project, and also submitted the lowest initial bid that was 10% under budget. We then worked with the owner to further enhance the project without cost increase. The project consists of a six-lane highway comprised of 60% bridges and 40% pavement above the area floodplain. KCI’s design-build team was prepared upon project award, and began construction three months after award, working through the harsh winter of 2010 and subsequently achieving project completion months ahead of schedule. We exceeded the workforce diversity and DBE subcontracting goals, while working over 150,000 manhours in a two year span with no OSHA violations.